| ID |
Tooling
Timeline |
Start |
End |
Duration |
| Jan 2005 |
Feb 2005 |
Mar 2005 |
| 1/2 |
1/9 |
1/16 |
1/23 |
1/30 |
2/6 |
2/13 |
2/20 |
2/27 |
3/6 |
3/13 |
3/20 |
3/27 |
|
|
| 1 |
Client provides drawing (or client approves Cypress
drawing) |
1/1/2005 |
1/2/2005 |
1d |
|
| 2 |
Cypress genereates tooling/piece part quote based
on drawing |
1/3/2005 |
1/6/2005 |
4d |
|
| 3 |
Client submits purchase order to Cypress with 50%
down payment with credit approval |
1/7/2005 |
1/13/2005 |
1w |
|
| 4 |
Cypress reviews and approves mold layout (with client
if applicable) |
1/14/2005 |
1/19/2005 |
4d |
|
| 5 |
Mold shop begins construction of tool based on approved drawings |
1/20/2005 |
2/18/2005 |
5w |
|
| 6 |
Cypress delivers T1 samples |
2/21/2005 |
2/24/2005 |
4d |
|
| 7 |
Client reviews samples and any necessary modifications
are made to the tool (if needed) |
2/25/2005 |
3/7/2005 |
10d |
|
| 8 |
After sample approved, tool is textured if specified
in the design |
3/8/2005 |
3/14/2005 |
1w |
|
| 9 |
T2 samples are run for customer approval, mold is
ready for production |
3/15/2005 |
3/18/2005 |
4d |
|