ID Tooling Timeline Start End Duration
Jan 2005 Feb 2005 Mar 2005
1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27
 
1 Client provides drawing (or client approves Cypress drawing) 1/1/2005 1/2/2005 1d
                       
2 Cypress genereates tooling/piece part quote based on drawing 1/3/2005 1/6/2005 4d
 
                     
3 Client submits purchase order to Cypress with 50% down payment with credit approval 1/7/2005 1/13/2005 1w
   
                   
4 Cypress reviews and approves mold layout (with client if applicable) 1/14/2005 1/19/2005 4d
   
                   
5 Mold shop begins construction of tool based on approved drawings 1/20/2005 2/18/2005 5w
   

 

         
6 Cypress delivers T1 samples 2/21/2005 2/24/2005 4d
               
         
7 Client reviews samples and any necessary modifications are made to the tool (if needed) 2/25/2005 3/7/2005 10d
               
       
8 After sample approved, tool is textured if specified in the design 3/8/2005 3/14/2005 1w
                   
   
9 T2 samples are run for customer approval, mold is ready for production 3/15/2005 3/18/2005 4d